Installation InstructionsDecoRidge® 8 Inch
DecoRidge® 8 Inch
Complete shingle application on roof deck before applying hip and ridge shingles. Hip shingles must be applied before applying ridge shingles. All hip and ridge shingles are applied with an 8 inch exposure.
Note: If a new roof is being applied over an existing roof, remove the old hip and ridge shingles to obtain a level application.
Use nails only when installing this product. Nails must be corrosion resistant, 11 or 12 gauge, with heads at least 3/8 inch in diameter.
Standard Fastening Pattern: One nail should be placed 8 1/2 inches back from the exposed end and 1 inch in for each side edge. (Fig. 1)
Application
- Begin hip application at the eave working toward the ridge.
1A. Begin ridge application opposite the prevailing wind direction. (Fig. 2) - Cut first hip and ridge 8" back from the exposed end. Use the top portion of the shingle with sealant as the “starter” hip or ridge shingle. (Fig. 2)
- Install this “starter” shingle positioned at the leading edge of the hip or ridge. Follow Standard Fastening Pattern in Fig. 1.
- Completely cover “starter” shingle with the 8" exposed portion of the next hip and ridge shingle. (Fig. 3)
- Fasten each shingle through the dimensional fold, following the Standard Fastening Pattern in Fig. 1. All nails must be covered by succeeding shingles. Apply remaining hip and ridge shingles in the same manner.
- Cut final ridge shingle from the 8" exposed portion of a hip and ridge shingle. Cut piece an appropriate length to the end of the ridge. (Fig. 4)
- Standard fastening pattern: Fasten final piece with two nails, 1" in from each side edge and 1" in from the end of the ridge. Cover nail with roof cement. (Fig. 4)